The Ministry of Trade and Industry has commissioned a
new fixed x-ray scanner at the port of Tema, Ghana.
The overall objective of this new modern process of examination
of goods is, by providing a non-intrusive inspection, to control imports
and to facilitate trade by checking the container and clearing the
documents in the minimum time. To allow this:
The use of the scanner is linked to to a computerised risk managamenent
system, which designates the containers to be scanned.
All administration for document clearance is conducted at one location
( single window system)
The energy for the x-ray equipment is 5 million electron
Volts (MeV), which although high is not dangerous to food items when
scanned or
workers/public on site. This scanner can penetrate up to 330mm of steel
allowing checking the majority of containers even with high density
goods inside.
To ensure radiation safety, the walls surrounding the
x-ray equipment are constructed of concrete up to 2.5 metres. The
tunnel is sealed
with 3 ton shielding doors.
Personnel in sensitive areas wear personal dosimeters , which record
the level of radiation received by each person, and there are also,
fixed dosimeters posted in key areas. This enables monitoring of the
radiation level in all areas of the site, ensuring that safety standards
are strictly adhered to.
The tunnel is designed to be of sufficient size to accept all road
worthy trucks carrying any size of container.
During the scanning sequence, the chain conveyor automatically pulls
the truck at a constant speed of 24 metres per minute through the x-ray
beam.
The process starts with appointment booking, arrival of container
and positioning of the truck in the tunnel.
A 40-foot container takes one minute from the start of scanning sequence
for images to be displayed on a screen. Well trained image analysts operate
three image workstations with one auditor monitoring their operations
from another workstation.
Image analysts take a few minutes to work on a image and communicate
their findings to the documentation office.
If a discrepancy is suspected between what is seen on the image and
the manifest information, the container will be directed to the recheck
area for examination.
The recheck office is fully equipped with a computer connected to
the main network allowing the officer to analyse the image first hand.
The checking platform is equipped to perform examination on two containers
simultaneously.
Movement of documents from one office to another
within Scanco is done electronically - a paperless transaction.
CRMS Value & Expected Action
Green CEPS Random = Random Inspection or immediate release
Yellow CEPS = CEPS Examination
Yellow Scanning = GSL Scanner
Red GSBV = GSBV Examination
Red CEPS = CEPS Examination
Therefore a percentage of imports will pass freely with
only a random inspection in the Green Channel. The Yellow Channel permits
some inspection and some scanning. The Red Channel permits physical
examination only by either Customs (CEPS) or GSBV.
The intention is that this process will ultimately reduce the amount
of physical examination required and speed up the customs clearance
process. Advantages will be less cargo handling, less port congestion
and ultimately a reduction in cost to the Ghanaian consumer.
Concerns over the new system are based on the ability of the unit
to cope with the required volumes (it can handle 1 x TEU every 10 minutes)
and the reliability of the sophisticated technology in such a demanding
operating environment.
New Scanner Installed at Tema Port
With effect from May 1st, 2004, all homogeneous full
container loads of food, drugs, and chemicals, including agro-chemicals
which constitute the bulk of high risk goods will be scanned at the
Tema port.
However, samples of the goods would be collected after
scanning from the premises of importers for testing and verification
by the
Ghana Standards Boards as to whether they conform to specifications
and standards, Mr. Alan Kyeremanten, Minister for Trade, Industry
and President Special Initiative (PSI) announced yesterday at Tema.
He
was commissioning a 3.2-million-dollar fixed gamma-ray container
cargo-scanning machine at the eastern gate of the Tema port.
The scanner,
the second
at the Tema port is to enhance trade facilitation to ensure that
bottlenecks in the clearing and forwarding of goods at the port were
reduced to
the barest minimum and also speed up clearance of goods.
Nick TC-Scan
Limited, a private company with Ghanaian and Chinese partners,
installed it. The three new inspection companies that were formed
in January
2003 to operate alongside Gateway Inspection Company jointly
operate the scanner. These companies are: 1. Inspection and Control
Services
2. Ghanalink Ltd 3. Bivac Ltd
The Gateway Services Limited (GSL)
and Scanning Company (SCANCO) installed the first scanning machine
in 1998.
The scanning machines had phased out the Pre-shipment Inspection
Scheme as well as the physical examination of goods, which delayed
clearing
procedure of cargo from the port.
Mr. Kyeremanten said it has
become necessary to reduce the number of consignments subjected
to physical
examination at customs from an average of 60% in 2002 to
an average of 10% for statutory free goods and 100% for dutiable goods
by
the end of 2004.
This is to reduce the dwell-time of containers
and the
turn-around time of ships. In this regard, the mandatory
physical
inspection of all high-risk goods, which constitute about
60% of total annual
imports of Ghana, has been reviewed, he stated.
The Ministry,
he said, is contemplating holding discussions with stakeholders
on the
possibility
of scanning some export goods at the Tema port and the
Kotoka International Airport to improve the overall security at the
port
and minimize
illegal shipments.
Vessel calls to the Port of Tema have registered a steady
increase.
Ship turnround time has been improving over the years except for 1999.
The increase in days was due to the dregging work that was undertaken
in the year 1999. The fast turnround time is a good means of savings
in terms of time and cost to customers.
Owing to the smooth accessibility of the port of Tema, its excellent
connections by road and inland waterways, its friendly and efficient
workforce, Tema Port has become an ideal port for the handling of transit
cargo for the landlocked countries of Burkina Faso, Mali and Niger.
The transit traffic has grown from a low level of 8,448 tonnes in 1997
to 261,251 tonnes in 2001.
The increase in transit cargo has been due to the realization that
transit customers have of the advantages Tema Port has over competing
ports in the sub-region. The decisive factors in the choice among others
include the following
Lower port tariffs
Quick turnround time
Shorter transit time
Safety of transit goods in the Port and along
the corridor
Infrastructure development to support growth - 15/07/08
The year 2007 marked Ghana’s seventh consecutive year of accelerating real
GDP growth and the fourth straight year of growth of 5% or better. Please click
here to read
Standard
Banks mid year gauge.
US$24.7m Loan Approved for Nsawam-Apedwa Road
- March 2004
A 24.7 million US dollar loan agreement between Ghana and the African
Development Fund (ADF) for the financing of the Nsawam-Apedwa road
project has been approved. The project would involve carrying out work
on the 41-kilometre Nsawam-Apedwa road and the construction of a new
10-kilometre bypass to the West of Nsawam Central Business District.
The Chairman of the Finance Committee, Mr Eugene Atta Agyepong said
the road when finished would enhance national economic activities,
movement of goods and people to markets, and facilitate regional trade
and economic integration.
Germany Provides US$13m For Accra-Kumasi Road
- March 2004
A grant of 13 million U.S dollars that was promised to the government
of Ghana by the Federal Republic of Germany, as its contribution toward
the cost of rebuilding the Accra-Kumasi road, is now ready to be issued
according to reports. The promise of the grant was made in response
to an appeal by President John Agyekum Kufuor during his state visit
to Germany in 2002. Mr. Linder gave the assurance that the German government
would continue to co-operate with Ghana in the areas of attracting
investment in agro-processing industry, boosting small-and medium-scale
enterprises and promoting good governance.
Construction company, appointed at the port
of Tema - 30/01/04
Interbeton, a third party construction company, has been
appointed for the bid to carry out improvements of the port of Tema.
A schedule has been circulated outlining the different stages of
the redevelopment as follows. Please click here for a map of the Tema port.
QUAY 2
Berth 1 & 2 - Draft 11.5m
This berth is currently closed until end of July 2004 earliest. For
guidance, 35 meters on berth #2 will be made available for berthing
with cargo for direct delivery until end of February, but as far as
large vessels are concerned, berthing is out of the question. The works
will be the demolition of shed #1, the removal of the existing pavement,
the installation of drainage, utilities, cranes and new pavement.
Berth 4 & 5 - Draft 9m
These berths should in theory remain open until the end of February.
From the 1st of March, the works carried out will be similar to Berth
#1 and #2, i.e. the demolition of shed #4 & 5 (to start respectively
in early May & March), the removal of the existing pavement, the
installation of drainage, utilities, cranes and new pavement. In other
words, berthing for large vessels will be "subject to accessibility" from
the 1st of March 2004. Barges working on the extension of berth 3,
2N and 4N will restrict the access of those berth.
Local shipping agencies have strongly stressed SOAAG to liase with
the constructors so that guarantees and dates are circulated so shipping
lines can be guaranteed at least one deep water berth during works.
SOAAG will revert on the developments of this issue.
QUAY 1
Quay #1 refers to berths 6 to 12. Draft 8m on all berths (tolerance
up to 8.25m maximum) These berths will run as normal except for the
following;
a) Sheds #8 and #10 - situated in front of berth # 8 & 10 - will
be reconstructed. The width of the quay will be reduced during the
works. Roro vessels relying on ramp usage for operations could be affected.
Accurate dates have not yet been circulated. The demolition of shed
4 & 5 was originally planned simultaneously, but this has apparently
changed.
b) The new Marine Dock will affect berthing of part of berth #12. Although
not all shipping lines are directly affected by works on Quay # 2 (having
smaller drafts than 8m), the reconstruction works in the port of Tema
will increase its congestion diverting most ships to Quay #1.
Tema buys three new Reach Stackers - Januray 2004
Ghana Ports and Harbours Authority (GPHA), has purchased
three new 45 tonnes Reach Stacker equipment at a cost of US$ 1,302,944.12
(11.3 billion cedis) to facilitate the lifting of containers to enhance
work at the Tema port. This brings the total to nine, 20 tonne Reach
Stackers and 13 for the 40 tonne Reach Stacker equipment that were
already operating at the Port.
The equipment was imported from SMV Lift Trucks of Sweden.
Mr Gordon Anim, Director of Tema Port, said the purchase of the equipment
became necessary due to the increase in cargo that passes through the
Port and response to complaints about delay in services of the Port.
In 2002 Tema port handled 230,000 TEUS containers but by the end of
October 2003, this had already risen to 252,000 containers. The Director
expressed the hope that the new equipment would help improve the services
at the Port and also help it to achieve its aim of being the gateway
to Ghana.
Ghana - Stevedoring to be Privatised
The GPHA Director General has confirmed that all stevedoring activities
in the Port of Tema will be privatised from the 1st of January 2004.
In this respect, the current organisation whereby GPHA allocates private
stevedores to vessels will seize, leaving the shipping lines - through
their agencies - to decide which private stevedores they want to hire.
Negotiations and agreements are therefore made directly between Stevedores
and Shipping Agents/Lines.
The Harbour Master will now be in charge of the allocation of berths
(formerly handled by the GPHA's Operations Manager).
Quay 2 Extension Project - Tema
The Quay 2 extension project has fallen behind schedule and can only
be completed on time if berths 1/2 are closed completely from 5th January
2004. Further details will be advised.
Tema Development Projects - Port Dredging
To position the port of Tema to meet the increasing challenges and
to attain the position of Gateway to West Africa, a number of expansion
and modernisation projects have been embarked on.
The Ghana Ports and Harbours Authority (GPHA) and the Dutch Government
have recently funded a $10.2-million project to dredge two berths at
the Tema Harbour. More than a third of the funding ($3.6m) comes from
the Dutch government, whilst the authority would also pay the remaining
$6.6 million. The dredging, being undertaken by a Dutch firm, Boskalis
International Bv, has been completed.
Due to the dredging, port congestion and vessels waiting
time has been drastically reduced. The access channel is now 12.5m,
whilst the inside area has been deepened to 11.5 meters.
Dredging of further berths to a maximum depth of 10 metres is scheduled
to commence in October 2002.
Tema Development Projects - Quay Extension
Plans have been made to extend Quay 2 by 200m, giving it a total length
of 570m. Quay 2 consists of the two deepest berths of 11.5m each.
Tema Development Projects - Private Sector Partnership
A further boost has been given to the port by increasing private sector
participation in theh port's cargo handling operations since July 2001.
The aim is to further reduce the total cost of doing business through
the port.
An international consortium made up of seven major players in the
international shipping industry is to take over the management of Tema
and Takoradi ports. The group also plans to invest $200 million in
developing them.
The consortium known as the 'Ghana Ports Service Consortium' (GPSC)
will be awarded a concession to manage the ports with the Ghanaian
government acting as landlords. The plan to privatise the ports is
aimed at increasing traffic through the ports headed for land-locked
countries in West Africa and is part of the on-going 'Ghana Gateway
Project'.
The project involves the extension and development of Quay Two into
a modern container terminal. While the Ghana Ports and Harbour Authority
(GPHA) will construct the first phase of the project, the Consortium
will engage in further developments and management of the facility.
The Consortium consists of AP Moeller Terminals,
Bathgate Management Limited, Beckett Rankine Partnership, Bouygues
Travaux Publics, Mersey
Docks and Harbour Company, SDV Ghana Limited (Bolloré Group)
and the Sutton Group.
Tema Port Handled Increased Cargo - March 2003
Transit cargo passing through the Tema Port increased to 627,773 tonnes
in 2002 compared 261,254 tonnes in 2001according to Mr Gorden Anim,
the Port Director. He attributed the increase to the political turmoil
in Cote d'Ivoire that had made the Abidjan port unsafe for port users
thus forcing the landlocked countries of Burkina Faso, Mali and Niger
to divert their cargo through Tema. For the last quarter of 2002, which
was October to December, the Port handled 255,080 tonnes of transit
cargo. Cargo that passed through the Tema Port included rice; sugar;
flour and containerised cargo. Containerised cargo was 32 per cent,
flour 13.5 per cent and steel/plates for constructional works was two
per cent. Mr Anim said that in 2000 the tonnage of transit cargo was
144,973 tonnes.
Consortium to run Ghana ports - November 2002
An international consortium made up of seven major players in the
international shipping industry is to take over the management of Tema
and Takoradi ports. The group also plans to invest $200 million in
developing them.
The consortium known as the 'Ghana Ports Service Consortium' (GPSC)
will be awarded a concession to manage the ports with the Ghanaian
government acting as landlords. The plan to privatise the ports is
aimed at increasing traffic through the ports headed for land-locked
countries in West Africa and is part of the on-going 'Ghana Gateway
Project'.
The project involves the extension and development of Quay Two into
a modern container terminal. While the Ghana Ports and Harbour Authority
(GPHA) will construct the first phase of the project, the Consortium
will engage in further developments and management of the facility.
The Consortium consists of AP Moeller Terminals,
Bathgate Management Limited, Beckett Rankine Partnership, Bouygues
Travaux Publics, Mersey
Docks and Harbour Company, SDV Ghana Limited (Bolloré Group)
and the Sutton Group.